Mindstream plans up to 400 MW AI campus in Jordan
Mindstream Energy targets an initial 70 MW deployment at its planned Al-Risha campus in the second quarter of 2027. The company estimates the first phase will require approximately $150 million to $400 million in infrastructure investment.

Mindstream Energy is targeting up to 400 megawatts of AI-ready data center capacity at a planned campus in Jordan, with an initial 70 MW deployment aimed for the second quarter of 2027. The company presented its plans for the Al-Risha campus at the Jordan–EU Investment Conference on Nov. 19.
The planned campus sits on a 250-acre site at Jordan’s natural gas field in Mafraq Governorate. Locally available natural gas is to supply dedicated on-site generation for a modular, off-grid development, with later expansion tied to customer demand.
Power and computing plans
The company has a natural gas supply agreement with Jordan’s National Petroleum Company. Its off-grid approach is intended to speed deployment and reduce reliance on utility grids.
The campus is designed for high-density AI and high-performance computing. Mindstream is targeting customers in Jordan, the Middle East and North Africa, Europe and beyond, including AI infrastructure customers, neoclouds and hyperscalers.
In July, Mindstream described plans for physically isolated computing zones with independent fiber connectivity and power distribution. Its plans also included recirculating cooling systems that would not require an external water source.
Investment depends on demand
Based on preliminary development scenarios, Mindstream estimates that the initial phase will represent approximately $150 million to $400 million in infrastructure investment. Long-term expansion could support cumulative infrastructure investment exceeding $1 billion, including solar photovoltaic system components, subject to customer demand, financing and phased development.
Compute investment could run into the billions, the company says. The development is designed to add capacity in stages rather than build the full campus at once.
Mindstream’s July announcement also described the campus as a platform for applications including AI model training and inference, research computing, sovereign cloud services and enterprise digital transformation. It said the platform may also support digital asset infrastructure.
Partners and connectivity
Mindstream says it has developed relationships with an ecosystem of 50 companies across areas including power, engineering, cooling, computing hardware, fiber connectivity, capital and prospective offtake. In September, the company said its relationships ranged from executed agreements to technical evaluation, commercial discussions and development collaboration.
An executed framework agreement with Park Place Technologies provides for the companies to evaluate opportunities across areas including AI infrastructure, high-performance computing, cloud computing and modular data centers. Mindstream has also selected Orange Jordan as its planned fiber-optic communications provider, with the companies intending to explore cooperation on connectivity and digital infrastructure at Al-Risha.
The two relationships are separate and do not represent a partnership or commercial relationship between Park Place Technologies and Orange Jordan, according to Mindstream’s August announcement.
Sources
- Original source · Press release Mindstream Energy · Powering jordans AI future Mindstream Energy unveils mw al… prnewswire.com
Other pages read
Related stories
- Cegedim opens French data center for AI and high-density computing
- Amazon Ties Up to $8 Billion in Generac Data Center Power
- Data center power demand tied to distant deaths in MIT study
- Nvidia’s private-company stakes reach $65.5 billion, TechCrunch reports
- NVIDIA reports Vera Rubin gains in MLPerf Training debut